86% of the 21,909 passenger trains whose arrival was recorded on Thursday, 27 August 2026 reached their destination within five minutes — an ordinary day, with the delays concentrated where they usually are.
Of 26,471 recorded runs, 439 did not run at all. Among those whose arrival reached the archive, 18,907 were within five minutes, 2,745 between five and thirty minutes down, and 257 more than half an hour — the tail that people actually remember.
“This service has been delayed by a late running train being in front of this one” was the most common explanation, given for 639 services.
Tyne and Wear Metro came closest to running to time, 98.2% of its 170 recorded arrivals; Chiltern Railways had the largest cancelled share at 13.4%.
An ordinary weekday timetable, with the two commuter peaks that give the network most of its work and least of its slack.
The day in numbers
| Passenger trains recorded | 26,471 | |
|---|---|---|
| Cancelled | 439 | 1.7% |
| Arrival time recorded | 21,909 | 84.2% of those that ran |
| …arrived within 5 minutes | 18,907 | 86.3% |
| …arrived 5 to 30 minutes late | 2,745 | 12.5% |
| …arrived more than 30 minutes late | 257 | 1.2% |
| Average delay at destination | 2.1 min |
Every percentage among the bands is of the 21,909 trains whose arrival reached the archive — not of all 26,471, and the bands are exclusive. 4,123 trains ran without an arrival time being recorded, and nothing is claimed about how punctual those were. Delay is judged at the destination, a stricter test than the industry's own measure and not comparable with it.
By operator
38 operators ran passenger services on this date, from ScotRail on 3,114 runs down to LS on 4. Ordered by volume, not performance — any heading re-sorts it.
| Operator | ||||||
|---|---|---|---|---|---|---|
ScotRail SR | 3,114 | 1% | 2,210 | 91% | 90% | 1.7 min |
Northern NT | 2,842 | 1% | 2,711 | 90% | 90% | 1.1 min |
Great Western Railway GW | 2,228 | 2% | 1,617 | 82% | 80% | 3.1 min |
South Western Railway SW | 1,904 | 1% | 1,586 | 91% | 90% | 1.2 min |
Southeastern SE | 1,826 | 1% | 1,794 | 90% | 89% | 1.3 min |
Southern SN | 1,790 | 2% | 1,636 | 82% | 81% | 2.4 min |
London Overground LO | 1,631 | 6% | 1,371 | 95% | 89% | 0.5 min |
Greater Anglia LE | 1,346 | 0% | 1,270 | 90% | 90% | 0.8 min |
West Midlands Railway LM | 1,333 | 3% | 1,240 | 83% | 81% | 3.1 min |
Transport for Wales AW | 1,303 | 1% | 1,012 | 88% | 86% | 1.4 min |
Thameslink TL | 953 | 2% | 585 | 84% | 82% | 2.2 min |
London Underground LT | 781 | 0% | 350 | 91% | 91% | 1.8 min |
Elizabeth line XR | 696 | 2% | 683 | 94% | 93% | 0.1 min |
Merseyrail ME | 622 | 0% | 612 | 98% | 97% | 0.4 min |
East Midlands Railway EM | 622 | 1% | 484 | 77% | 76% | 2.9 min |
c2c CC | 536 | 3% | 363 | 82% | 79% | 2.5 min |
Great Northern GN | 431 | 3% | 371 | 72% | 70% | 4.7 min |
Avanti West Coast VT | 387 | 2% | 273 | 26% | 25% | 18.7 min |
Chiltern Railways CH | 351 | 13% | 304 | 89% | 77% | 1.6 min |
CrossCountry XC | 350 | 1% | 278 | 53% | 52% | 9.4 min |
TransPennine Express TP | 345 | 1% | 317 | 82% | 80% | 2.7 min |
London North Eastern Railway GR | 322 | 1% | 193 | 38% | 38% | 14 min |
Tyne and Wear Metro TW | 174 | 0% | 170 | 98% | 98% | 0.2 min |
Heathrow Express HX | 152 | 0% | 152 | 92% | 92% | 1.3 min |
Sheffield Supertram SJ | 98 | 0% | 74 | 100% | 100% | 0.5 min |
Gatwick Express GX | 72 | 3% | 66 | 61% | 59% | 6.2 min |
Eurostar ES | 53 | 0% | 53 | 75% | 75% | 5.1 min |
Island Line IL | 52 | 2% | 50 | 100% | 98% | -0.1 min |
Charter/Other ZZ | 51 | 0% | 3 | 100% | 100% | 2.7 min |
West Coast Railway Co WR | 24 | 0% | 10 | 60% | 60% | 26 min |
Grand Central GC | 20 | 0% | 20 | 20% | 20% | 15.2 min |
Hull Trains HT | 14 | 0% | 14 | 36% | 36% | 10.4 min |
Lumo LD | 12 | 0% | 12 | 8% | 8% | 18.8 min |
Lumo Stirling LF | 10 | 0% | 10 | 30% | 30% | 16.8 min |
Caledonian Sleeper CS | 10 | 30% | 7 | 71% | 50% | -7.7 min |
North Yorkshire Moors Railway NY | 8 | 0% | 8 | 88% | 88% | -30.6 min |
TY TY | 4 | 0% | 0 | — | — | — |
LS LS | 4 | 0% | 0 | — | — | — |
“On time” is of each operator's recorded arrivals; “incl. cancelled” counts a cancellation as a failure, which is what the industry's own measure does. Across the whole day they read 86% and 85% — why both are published, what each hides, and how the sort treats a small operator.
Why trains were late
8 different reasons were given for delay on this date, each reproduced in the operator's own words.
This service has been delayed by a late running train being in front of this one
639 services
This service has been delayed by a speed restriction
619 services
This service has been delayed by a speed restriction over defective track
272 services
This service has been delayed by a fault with the signalling system
244 services
This service has been delayed by congestion
218 services
This service has been delayed by a problem currently under investigation
177 services
This service has been delayed by a safety inspection of the track
156 services
This service has been delayed by a fault on this train
88 services
Why trains were cancelled
A reason reached the archive for 242 of the 439 cancellations (55.1%), across 8 distinct reasons. A run cancelled part-way along often carries no reason at all.
This service has been cancelled because of a shortage of train drivers
63 services
This service has been cancelled because of a late running train being in front of this one
53 services
This service has been cancelled because of a fault with the signalling system
50 services
This service has been cancelled because of a fault on this train
25 services
This service has been cancelled because of damage to the overhead electric wires
15 services
This service has been cancelled because of an operational incident earlier today
13 services
This service has been cancelled because of more trains than usual needing repairs at the same time
12 services
This service has been cancelled because of a safety inspection of the track
11 services
The longest delays
The worst of them arrived 6h 05m behind schedule — Alloa to Glasgow Queen Street, booked away at 10:15, run by ScotRail. The ten longest range from 6h 05m down to 1h 45m, and they belong to 5 operators, ScotRail accounting for 3. What a delay on that scale usually means.
| Booked | Service | Late by |
|---|---|---|
10:15 | Alloa to Glasgow Queen Street 2N42 · SR | 6h 05m |
09:05 | Aberdeen to Edinburgh 1B74 · SR | 2h 09m |
21:56 | Newbury to London Paddington 1K37 · GW | 2h 05m |
22:30 | London Paddington to Bristol Temple Meads 1C37 · GW | 2h 02m |
07:55 | Inverness to London Kings Cross 1E13 · GR | 2h 00m |
21:17 | Abbey Wood to Reading 9R76 · XR | 1h 57m |
21:44 | Didcot Parkway to London Paddington 2P86 · GW | 1h 54m |
10:20 | Leven to Edinburgh 2K60 · SR | 1h 53m |
12:50 | Fort William to Mallaig 2Y68 · WR | 1h 51m |
21:32 | Abbey Wood to Maidenhead 9N80 · XR | 1h 45m |
Through the day
Booked departures by hour, with the share that arrived within five minutes. Punctuality was weakest at 00:00, when 56% of 158 arrived within five minutes.
The filled part of each bar is the share of that hour's booked departures that arrived within five minutes. The quietest was 02:00 with 14.
What ran
Formations were recorded for 27,059 trains on this date, made up of 2,898 individual units and 12,725 separate vehicles. These figures cover the services an allocation was published for, not every train that ran.
25 different classes of train appeared, which is the signature of a full weekday — the long-distance fleets, the regional diesel units and the suburban electrics all working at once.
The most-used class was the 377, allocated to 3,297 of the day's recorded trains from a pool of 219 units.
The average train was 5.6 vehicles long. The longest formation recorded was 18 vehicles.
| Class | Trains | Units used |
|---|---|---|
| Class 377 | 3,297 | 219 |
| Class 465 | 1,654 | 103 |
| Class 720 | 1,615 | 129 |
| Class 450 | 1,494 | 117 |
| Class 158 | 1,444 | 133 |
| Class 387 | 1,426 | 97 |
| Class 150 | 1,323 | 90 |
| Class 345 | 1,293 | 68 |
| Class 165 | 1,188 | 64 |
| Class 156 | 1,112 | 93 |
| Class 375 | 1,044 | 102 |
| Class 385 | 997 | 65 |
Of 26,471 runs, 27,059 had a formation published (102%) — these are allocations rather than observations.
Buses
16,254 buses from 163 operators were seen on this date, across 2,906,038 position reports.
132,132 bus journeys were followed to their destination on this date. 92,257 arrived on time, 6,407 late, and 33,468 — 25% — arrived ahead of schedule.
Early arrivals are normal rather than exceptional. Bus running times carry enough slack to survive traffic, and it is concentrated in the last leg, so a clear run simply finishes sooner than booked.
Averaged across every journey, buses arrived 0.2 minutes ahead of schedule — the early arrivals outweighing the late ones.
| Journeys followed to destination | 132,132 | |
|---|---|---|
| On time | 92,257 | 69.8% |
| Early | 33,468 | 25.3% |
| Late | 6,407 | 4.8% |
| …more than 20 minutes late | 651 | 0.5% |
| Average arrival | 0.2 min early |
By operator
| Operator | Journeys | On time | Early |
|---|---|---|---|
Transport for London TFLO | 99,945 | 72% | 25% |
Nottingham City Transport NCTR | 2,617 | 76% | 22% |
Go North East GNEL | 2,057 | 78% | 11% |
First South Yorkshire FSYO | 1,868 | 59% | 33% |
First Bristol, Bath & the West FBRI | 1,648 | 57% | 31% |
First Leeds FLDS | 1,616 | 55% | 38% |
Bee Network BNSM | 920 | 77% | 19% |
Arriva Yorkshire WRAY | 895 | 56% | 35% |
National Express NATX | 839 | 28% | 35% |
First Potteries FPOT | 786 | 51% | 43% |
National Express West Midlands TNXB | 783 | 80% | 16% |
Bee Network BNML | 608 | 71% | 25% |
Of the operators with enough journeys to compare, Uni-Link ran closest to time (86%), and National Express furthest from it (28%).