Tuesday, 13 October 2026
87% of the 21,780 passenger trains whose arrival was recorded on Tuesday, 13 October 2026 reached their destination within five minutes — an ordinary day, with the delays concentrated where they usually are.
Of 25,796 recorded runs, 403 did not run at all. Among those whose arrival reached the archive, 18,953 were within five minutes, 2,657 between five and thirty minutes down, and 170 more than half an hour — the tail that people actually remember.
“This service has been delayed by a late running train being in front of this one” was the most common explanation, given for 594 services.
Merseyrail came closest to running to time, 99.3% of its 603 recorded arrivals; Thameslink had the largest cancelled share at 5.3%.
An ordinary weekday timetable, with the two commuter peaks that give the network most of its work and least of its slack.
Buses on this date: 141,187 journeys followed to their destination, 71.4% on time.
The day in numbers
| Passenger trains recorded | 25,796 | |
|---|---|---|
| Cancelled | 403 | 1.6% |
| Arrival time recorded | 21,780 | 85.8% of those that ran |
| …arrived within 5 minutes | 18,953 | 87.0% |
| …arrived 5 to 30 minutes late | 2,657 | 12.2% |
| …arrived more than 30 minutes late | 170 | 0.8% |
| Average delay at destination | 1.8 min |
Every percentage among the bands is of the 21,780 trains whose arrival reached the archive — not of all 25,796, and the bands are exclusive. 3,613 trains ran without an arrival time being recorded, and nothing is claimed about how punctual those were. Delay is judged at the destination, a stricter test than the industry's own measure and not comparable with it.
By operator
37 operators ran passenger services on this date, from ScotRail on 2,980 runs down to North Yorkshire Moors Railway on 8. Ordered by volume, not performance — any heading re-sorts it.
| Operator | ||||||
|---|---|---|---|---|---|---|
ScotRail SR | 2,980 | 1% | 2,138 | 91% | 90% | 1.4 min |
Northern NT | 2,806 | 1% | 2,663 | 87% | 86% | 1.6 min |
Great Western Railway GW | 2,155 | 1% | 1,623 | 90% | 89% | 1.1 min |
Southeastern SE | 1,801 | 3% | 1,695 | 81% | 78% | 3 min |
South Western Railway SW | 1,712 | 3% | 1,512 | 88% | 86% | 1.3 min |
Southern SN | 1,692 | 3% | 1,582 | 83% | 80% | 2.5 min |
London Overground LO | 1,589 | 2% | 1,549 | 97% | 95% | -0.2 min |
West Midlands Railway LM | 1,320 | 1% | 1,264 | 85% | 84% | 2 min |
Greater Anglia LE | 1,313 | 1% | 1,295 | 96% | 95% | 0 min |
Transport for Wales AW | 1,237 | 1% | 1,026 | 94% | 92% | -0.2 min |
Thameslink TL | 965 | 5% | 562 | 81% | 75% | 2.3 min |
Merseyrail ME | 800 | 0% | 603 | 99% | 99% | 0.1 min |
London Underground LT | 774 | 0% | 363 | 96% | 96% | 1.3 min |
Elizabeth line XR | 688 | 1% | 674 | 99% | 98% | -0.8 min |
East Midlands Railway EM | 615 | 1% | 480 | 69% | 68% | 4.9 min |
Avanti West Coast VT | 420 | 1% | 311 | 54% | 54% | 8.5 min |
Great Northern GN | 419 | 1% | 382 | 83% | 82% | 2.7 min |
c2c CC | 416 | 3% | 349 | 81% | 78% | 2.9 min |
CrossCountry XC | 349 | 2% | 272 | 51% | 50% | 11 min |
Chiltern Railways CH | 341 | 4% | 328 | 92% | 89% | 1.1 min |
TransPennine Express TP | 335 | 2% | 312 | 74% | 72% | 4.5 min |
London North Eastern Railway GR | 328 | 1% | 193 | 60% | 59% | 10.4 min |
Tyne and Wear Metro TW | 170 | 0% | 133 | 92% | 92% | 2.1 min |
Heathrow Express HX | 150 | 0% | 150 | 97% | 97% | 0.3 min |
Sheffield Supertram SJ | 98 | 0% | 67 | 88% | 88% | 1.5 min |
Gatwick Express GX | 72 | 0% | 72 | 72% | 72% | 4.2 min |
Island Line IL | 52 | 2% | 50 | 84% | 82% | 1.3 min |
Eurostar ES | 49 | 0% | 48 | 83% | 83% | 3.3 min |
Charter/Other ZZ | 47 | 0% | 4 | 75% | 75% | -3.2 min |
Grand Central GC | 20 | 0% | 20 | 35% | 35% | 16.2 min |
West Coast Railway Co WR | 18 | 0% | 6 | 100% | 100% | -9.7 min |
Hull Trains HT | 15 | 0% | 15 | 40% | 40% | 19.3 min |
Lumo LD | 12 | 0% | 11 | 36% | 36% | 15.9 min |
LS LS | 10 | 0% | 2 | 100% | 100% | 2.5 min |
Lumo Stirling LF | 10 | 0% | 10 | 70% | 70% | 4.3 min |
Caledonian Sleeper CS | 10 | 0% | 8 | 75% | 75% | -6.6 min |
North Yorkshire Moors Railway NY | 8 | 0% | 8 | 88% | 88% | -35.2 min |
“On time” is of each operator's recorded arrivals; “incl. cancelled” counts a cancellation as a failure, which is what the industry's own measure does. Across the whole day they read 87% and 85% — why both are published, what each hides, and how the sort treats a small operator.
Why trains were late
8 different reasons were given for delay on this date, each reproduced in the operator's own words.
This service has been delayed by a late running train being in front of this one
594 services
This service has been delayed by a speed restriction
553 services
This service has been delayed by congestion
324 services
This service has been delayed by a speed restriction over defective track
247 services
This service has been delayed by a problem in the depot
195 services
This service has been delayed by a safety inspection of the track
192 services
This service has been delayed by a fault with the signalling system
169 services
This service has been delayed by a late running freight train
145 services
Why trains were cancelled
A reason reached the archive for 190 of the 403 cancellations (47.1%), across 8 distinct reasons. A run cancelled part-way along often carries no reason at all.
This service has been cancelled because of a problem in the depot
36 services
This service has been cancelled because of a fault on this train
31 services
This service has been cancelled because of a safety inspection of the track
27 services
This service has been cancelled because of a fault with the signalling system
26 services
This service has been cancelled because of trespassers on the railway
20 services
This service has been cancelled because of a fault on a train
19 services
This service has been cancelled because of the emergency services dealing with an incident earlier today
16 services
This service has been cancelled because of a tree blocking the railway
15 services
The longest delays
The worst of them arrived 2h 52m behind schedule — London Kings Cross to Newcastle, booked away at 19:33, run by London North Eastern Railway. The ten longest range from 2h 52m down to 1h 18m, and they belong to 7 operators, London North Eastern Railway accounting for 3. What a delay on that scale usually means.
| Booked | Service | Late by |
|---|---|---|
19:33 | London Kings Cross to Newcastle 1N14 · GR | 2h 52m |
18:45 | Reading to Newcastle 1E68 · XC | 2h 21m |
18:12 | Aberdeen to York 1E31 · GR | 2h 13m |
20:33 | London Kings Cross to Newcastle 1N15 · GR | 2h 09m |
10:27 | Shrewsbury to Aberystwyth 1J09 · AW | 2h 05m |
20:24 | Liverpool Lime Street to Newcastle 9E20 · TP | 1h 50m |
09:24 | Ashford International to Eastbourne 2D15 · SN | 1h 42m |
10:24 | Ashford International to Eastbourne 2D19 · SN | 1h 36m |
10:36 | Middlesbrough to Carlisle 1J59 · NT | 1h 27m |
11:26 | London Cannon Street to London Cannon Street 2P31 · SE | 1h 18m |
Through the day
Booked departures by hour, with the share that arrived within five minutes. Punctuality was weakest at 04:00, when 62% of 158 arrived within five minutes.
The filled part of each bar is the share of that hour's booked departures that arrived within five minutes. The quietest was 02:00 with 16.
What ran
Formations were recorded for 27,097 trains on this date, made up of 2,912 individual units and 12,851 separate vehicles. These figures cover the services an allocation was published for, not every train that ran.
25 different classes of train appeared, which is the signature of a full weekday — the long-distance fleets, the regional diesel units and the suburban electrics all working at once.
The most-used class was the 377, allocated to 3,343 of the day's recorded trains from a pool of 221 units.
The average train was 5.6 vehicles long. The longest formation recorded was 24 vehicles.
| Class | Trains | Units used |
|---|---|---|
| Class 377 | 3,343 | 221 |
| Class 465 | 1,645 | 100 |
| Class 450 | 1,553 | 119 |
| Class 720 | 1,533 | 131 |
| Class 150 | 1,461 | 90 |
| Class 387 | 1,389 | 95 |
| Class 158 | 1,363 | 132 |
| Class 345 | 1,264 | 70 |
| Class 165 | 1,168 | 61 |
| Class 156 | 1,074 | 89 |
| Class 700 | 1,036 | 109 |
| Class 375 | 1,034 | 103 |
Of 25,796 runs, 27,097 had a formation published (105%) — these are allocations rather than observations.
Buses
17,647 buses from 191 operators were seen on this date, across 3,223,895 position reports.
141,187 bus journeys were followed to their destination on this date. 100,865 arrived on time, 8,295 late, and 32,027 — 23% — arrived ahead of schedule.
Early arrivals are normal rather than exceptional. Bus running times carry enough slack to survive traffic, and it is concentrated in the last leg, so a clear run simply finishes sooner than booked.
The average arrival was 0.1 minutes late, and 872 journeys finished more than fifteen minutes down.
| Journeys followed to destination | 141,187 | |
|---|---|---|
| On time | 100,865 | 71.4% |
| Early | 32,027 | 22.7% |
| Late | 8,295 | 5.9% |
| …more than 15 minutes late | 872 | 0.6% |
| Average arrival | 0.1 min late |
By operator
| Operator | Journeys | On time | Early |
|---|---|---|---|
Transport for London TFLO | 107,734 | 74% | 23% |
Nottingham City Transport NCTR | 2,447 | 76% | 17% |
Go North East GNEL | 2,070 | 69% | 9% |
First South Yorkshire FSYO | 2,026 | 59% | 23% |
First Leeds FLDS | 1,674 | 60% | 28% |
First Bristol, Bath & the West FBRI | 1,507 | 58% | 24% |
Arriva Yorkshire WRAY | 886 | 53% | 31% |
Bee Network BNSM | 884 | 75% | 19% |
First Potteries FPOT | 866 | 55% | 32% |
National Express West Midlands TNXB | 842 | 75% | 18% |
First Leicester FLEI | 758 | 59% | 37% |
National Express NATX | 755 | 35% | 31% |
Of the operators with enough journeys to compare, Uni-Link ran closest to time (91%), and National Express furthest from it (35%).
Our figures, not the regulator's — why buses run early, the current league.
Recorded live from the Darwin and TRUST feeds on 13 Oct 2026 itself. How these figures are measured · Sources and licences